Design B - left in and left out of Harris Street

CLOSED: This discussion has concluded.

Features - what the proposed design involves

  • Install a raised traffic island on Lutwyche Road to:
    • restrict the right turn movement out of Harris Street into Lutwyche Road
    • restrict the right turn movement from Lutwyche Road into Harris Street.
  • Upgrade and relocate the traffic signals to realign the signalised crossing further south on Lutwyche Road.
  • Resume land on the south-west corner of the intersection and undertake reinstatement works to allow for the reconstruction and widening of footpath.


Benefits - why we are proposing the feature of this design

  • Improve safety for all road users by removing the right turn out of Harris Street into Lutwyche Road, eliminating any potential for conflict.
  • Improve safety for motorists on Lutwyche Road by removing the right turn movement into Harris Street from Lutwyche Road, eliminating any potential for conflict.
  • Improve connectivity and promote a safer environment for people walking through the area by:
    • relocating the signalised crossing on Lutwyche Road further south to provide a better alignment
    • removing the right turn out of Harris Street to ensure no potential for conflicts
    • installing raised traffic islands to provide better protection
    • upgrade and widen footpath and kerb ramps.
  • Maintain left in and left out turn movement of Harris Street.


Considerations - things to consider about this proposed design

  • No right turn permitted into or out of Harris Street.
  • Resumption of land on the south-west corner of the intersection entails a lengthy legal process before construction works can commence.
  • New travel routes will be required for motorists:

Community engagement on the Lutwyche Road and Harris Street intersection upgrade has now closed.  Thank you to everyone who has provided feedback.